A Jira Cloud app that turns a set of Jira projects into a one-page stakeholder status report in one click.

Coming soon to the Atlassian Marketplace. Questions before then? Email krish.c@nineiq.co.

What you get

You define a program, for example "Checkout replatform" made of projects WEB, PAY and MOB. The app reads every epic and its child work items and gives you:

  • Overall health (On track, At risk or Off track) and progress across the whole program.
  • Epics, worst first, with owner, due date, percent done and the reason for each rating. Epics whose rating changed since the last report are marked.
  • Blockers and cross-team dependencies: blocked or flagged work items, and open "blocks" links between projects.
  • Risks: work items of type Risk, or labelled risk or raid-risk.
  • This week: what finished, what was added and what is due in the next 14 days.
  • Data gaps: epics with no due date, no owner or no child work items.
  • Copy report: the whole report as Markdown, ready to paste into Confluence, Slack or an email.

Getting started

  1. A Jira site admin installs Program Status Report from the Atlassian Marketplace.
  2. In Jira, open Apps, then Program Status Report.
  3. Choose New program, give it a name, and enter the Jira project keys that make up the program, or your own JQL.
  4. Optionally adjust the At risk and Off track thresholds for this program, then save.
  5. Press Build report. Use the Copy report tab to paste it wherever your stakeholders read it.

How ratings work

Ratings compare how much work is done with how much of the epic's time has been used. Time used runs from the epic's start date (or created date) to its due date.

RatingRule
DoneThe epic is in a Done status.
No dateThe epic has no due date, so it can't be rated. It is listed under Data gaps.
Off trackPast its due date, or percent done is more than 25 points behind percent of time used.
At riskPercent done is more than 10 points behind percent of time used, or a child work item is blocked.
On trackEverything else.

Both thresholds (10 and 25 points by default) can be changed per program. The overall program rating is the worst epic rating.

Blockers and risks

A work item counts as blocked when its status contains "block", "impediment" or "on hold", it has the label blocked, or Jira's Flagged field is set. Risks are work items of type Risk, or with the label risk or raid-risk. Cross-team dependencies are open "blocks" links between work items in different projects.

Limits

  • One report reads up to 200 epics and 2,000 child work items. The page tells you when a program is bigger than that.
  • On paid installs, saving programs and building reports need an active license. Without one, the page still opens and shows saved programs.

Permissions and data

  • Jira is read as the person who opens the page, so people only see work items they already have access to.
  • The app asks for read-only scopes: read:jira-work, read:jira-user and storage:app. It cannot change your Jira data.
  • It stores only your saved programs and the last rating of each epic, in Atlassian's Forge storage. Nothing is sent to NineIQ or anyone else.

Read the full privacy policy.

Support

Email krish.c@nineiq.co with your Jira site address and a short description of what you see. We reply by email.